No. 52 Wednesday, February 10, 2010
The Jamaica Public Service Co, Ltd. (JPS), has unveiled its plans for the Munro Wind Energy Project, to the residents of St. Elizabeth.
The Jamaica Public Service Co, Ltd. (JPS), has unveiled its plans for the Munro Wind Energy Project, to the residents of St. Elizabeth.
The unveiling took place at a public meeting held on Thursday, February 5, at the Munro College, which saw residents from Hermitage and the surrounding communities keen on gleaning information about the development which will take place in their parish.
JPS Project Planning and Development Analyst, Richard Gordon, presented a technical overview of the project, which among other things explained the suitability of the Hermitage/Munro location from which the power of the North East Trade Winds will be harvested.
The four wind turbines, which are slated for installation by the 4th quarter of 2010, will have a lifetime of
20 years, and are designed to withstand storm winds of up to 150 miles per hour. The project, he explained, is part of an overall thrust to increase the use of renewable energy sources, from just under 5%, to 15% by the year 2015.
Residents were also guided through the Environmental Impact Assessment report which was prepared by independent environmental consultants, Environmental and Engineering Managers Ltd., and presented by Mrs. Ianthe Smith.
The group was assured that the environmental footprint of the project would be a small one, with the development leaving no deleterious effects on the plant or animal life of the environment.
The session was also used to inform members of the community of the need for preparatory road works, to facilitate the transportation of heavy equipment. Movement of such equipment will take place at night between the hours of 1:00 and 4:00 a.m., to minimize disruption for road users.
The construction period of the project will also see the creation of at least 60 jobs for members of the local community, in both skilled and unskilled capacities.
Mayor of Black River, His Worship Jeremy Palmer, expressed pleasure at the power Company's attention to developing renewable energy sources. Mayor Palmer told the audience that he had been briefed on the project from its earliest planning stages and was looking forward to its completion.
JPS will continue to have dialogue with the community as the development progresses.
The Munro renewable project, is expected to add 3 megawatts of electricity to the national grid.
Marubeni TAQA Caribbean (MTC) owns 80% of the shares in JPS. The Government of Jamaica and a small group of minority shareholders own the remaining shares.